spaschal on DSK3GDR082PROD with CFR Federal Aviation Administration, DOT Section 26.33 (i) Fuel tanks for which the type certificate holder has notified the FAA under paragraph (g) of this section that it will provide design changes and service instructions for Flammability Reduction Means or an Ignition Mitigation Means (IMM) meeting the requirements of paragraph (c) of this section. (ii) Fuel tanks substantiated to be conventional unheated aluminum wing tanks. (c) Design Changes. For fuel tanks with a Fleet Average Flammability Exposure exceeding 7 percent, one of the following design changes must be made. (1) Flammability Reduction Means (FRM). A means must be provided to reduce the fuel tank flammability. (i) Fuel tanks that are designed to be Normally Emptied must meet the flammability exposure criteria of Appendix M of part 25 of this chapter if any portion of the tank is located within the fuselage contour. (ii) For all other fuel tanks, the FRM must meet all of the requirements of Appendix M of part 25 of this chapter, except, instead of complying with paragraph M25.1 of this appendix, the Fleet Average Flammability Exposure may not exceed 7 percent. (2) Ignition Mitigation Means (IMM). A means must be provided to mitigate the effects of an ignition of fuel vapors within the fuel tank such that no damage caused by an ignition will prevent continued safe flight and landing. (d) Service Instructions. No later than December 27, 2010, holders of type certificates required by paragraph (c) of this section to make design changes must meet the requirements specified in either paragraph (d)(1) or (d)(2) of this section. The required service instructions must identify each airplane subject to the applicability provisions of paragraph (a) of this section. (1) FRM. The type certificate holder must submit for approval by the responsible Aircraft Certification Service office design changes and service instructions for installation of fuel tank flammability reduction means (FRM) meeting the criteria of paragraph (c) of this section. (2) IMM. The type certificate holder must submit for approval by the responsible Aircraft Certification Service office design changes and service instructions for installation of fuel tank IMM that comply with 14 CFR 25.981(c) in effect on December 26, 2008. (e) Instructions for Continued Airworthiness (ICA). No later than December 27, 2010, holders of type certificates required by paragraph (c) of this section to make design changes must submit for approval by the responsible Aircraft Certification Service office, critical design configuration control limitations (CDCCL), inspections, or other procedures to prevent increasing the flammability exposure of any tanks equipped with FRM above that permitted under paragraph (c)(1) of this section and to prevent degradation of the performance of any IMM provided under paragraph (c)(2) of this section. These CDCCL, inspections, and procedures must be included in the Airworthiness Limitations Section (ALS) of the ICA required by 14 CFR 25.1529 or paragraph (f) of this section. Unless shown to be impracticable, visible means to identify critical features of the design must be placed in areas of the airplane where foreseeable maintenance actions, repairs, or alterations may compromise the critical design configuration limitations. These visible means must also be identified as a CDCCL. (f) Airworthiness Limitations. Unless previously accomplished, no later than December 27, 2010, holders of type certificates affected by this section must establish an ALS of the maintenance manual or ICA for each airplane configuration evaluated under paragraph (b)(1) of this section and submit it to the responsible Aircraft Certification Service office for approval. The ALS must include a section that contains the CDCCL, inspections, or other procedures developed under paragraph (e) of this section. (g) Compliance Plan for Flammability Exposure Analysis. Within 90 days after December 26, 2008, each holder of a type certificate required to comply with paragraph (b) of this section must submit to the responsible Aircraft Certification Service office a compliance plan consisting of the following: (1) A proposed project schedule for submitting the required analysis, or a determination that compliance with 477 VerDate Sep<11>2014 12:50 Apr 30, 2019 Jkt 247046 PO 00000 Frm 00487 Fmt 8010 Sfmt 8010 Y:\SGML\247046.XXX 247046