Section 152.321 14 CFR Ch. I (1-1-19 Edition) (2) The reasons for slippage in each case where an established goal was not met; and (3) Other pertinent information including, when appropriate, an analysis and explanation of each cost overrun and high unit cost. (d) Airport planning. The sponsor of a project for airport master planning or a planning agency conducting a project for airport system planning shall submit a performance report, on a quarterly basis, that must include: (1) A comparison of actual accomplishments to the goals established for the period, made, if applicable, on a quantitative basis related to costs for computation of work element costs; (2) Reasons for slippage in each case where an established goal was not met; and (3) Other pertinent information including, when appropriate, an analysis and explanation of each cost overrun and high work element cost. Section 152.321 Notice of delay or acceleration. (a) The sponsor or planning agency shall promptly notify the FAA of each condition or event that may delay or accelerate accomplishment of the project. (b) In the event that delay is anticipated, the notice required by paragraph (a) of this section must include - (1) A statement of actions taken or contemplated; and (2) Any Federal assistance needed. Section 152.323 Budget revision: Airport development. (a) If any performance review conducted by the sponsor discloses a need for change in the budget estimates, the sponsor shall submit a request for budget revision on a form prescribed by the Administrator. (b) A request for prior approval for budget revision shall be made promptly by the sponsor whenever - (1) The revision results from changes in the scope or objective of the project; or (2) The revision increases the budgeted amounts of Federal funds needed to complete the project. (c) The sponsor shall promptly notify the FAA whenever the amount of the grant is expected to exceed the needs of the sponsor by more than $5,000, or 5 percent of the grant amount, whichever is greater. Section 152.325 Financial status report: Airport planning. Each sponsor of a project for airport master planning and each planning agency conducting a project for airport system planning shall submit a financial status report on a form prescribed by the Administrator at the completion of the project. Subpart E - Nondiscrimination in Airport Aid Program AUTHORITY: Sec. 30 of the Airport and Airway Development Act of 1970 (49 U.S.C. 1730); sec. 1.47(f)(1) of the Regulations of the Office of the Secretary of Transportation (49 CFR 1.47(f)(1)). SOURCE: Docket No. 16419, 45 FR 10188, Feb. 14, 1980, unless otherwise noted. Section 152.401 Applicability. (a) This subpart is applicable to all grantees and other covered organizations under this part, and implements the requirements of section 30 of the Airport and Airway Development Act of 1970, which provides: The Secretary shall take affirmative action to assure that no person shall, on the grounds of race, creed, color, national origin, or sex, be excluded from participating in any activity conducted with funds received from any grant made under this title. The Secretary shall promulgate such rules as he deems necessary to carry out the purposes of this section and may enforce this section, and any rules promulgated under this section, through agency and department provisions and rules which shall be similar to those established and in effect under Title VI of the Civil Rights Act of 1964. The provisions of this section shall be considered to be in addition to and not in lieu of the provisions of Title VI of the Civil Rights Act of 1964. (b) Each grantee, covered organization, or covered suborganization under this part shall negotiate reformation of any contract, subcontract, lease, sublease, or other agreement to include any appropriate provision necessary to effect compliance with this subpart by July 17, 1980. 726 VerDate Sep<11>2014 08:20 May 17, 2019 Jkt 247048 PO 00000 Frm 00736 Fmt 8010 Sfmt 8010 Y:\SGML\247048.XXX 247048