| Previous Page | Page 130 | Next Page |
121
Federal Aviation Administration, DOT
§ 17.33
§ 17.33
Adjudicative Process for con-
tract disputes.
(a) The Adjudicative Process for con-
tract disputes will be commenced by
the ODRA Director upon being notified
by the ADR neutral or by any party
that either—
(1) The parties will not be attempting
ADR; or
(2) The parties have not settled all of
the dispute issues via ADR, and it is
unlikely that they can do so within the
time period allotted and/or any reason-
able extension.
(b) In cases initiated by a contractor
against the FAA, within twenty (20)
business days of the commencement of
the Adjudicative Process or as sched-
uled by the ODRA, the Product Team
shall prepare and submit to the ODRA,
with a copy to the contractor, a chron-
ologically arranged and indexed sub-
stantive response, containing a legal
and factual position regarding the dis-
pute and all documents relevant to the
facts and issues in dispute. The con-
tractor will be entitled, at a specified
time, to supplement the record with
additional documents.
(c) In cases initiated by the FAA
against a contractor, within twenty
(20) business days of the commence-
ment of the Adjudicative Process or as
scheduled by the ODRA, the contractor
shall prepare and submit to the ODRA,
with a copy to the Product Team coun-
sel, a chronologically arranged and in-
dexed substantive response, containing
a legal and factual position regarding
the dispute and all documents relevant
to the facts and issues in dispute. The
Product Team will be entitled, at a
specified time, to supplement the
record with additional documents.
(d) Unless timely objection is made,
documents properly filed with the
ODRA will be deemed admitted into
the administrative record. Discovery
requests and responses are not part of
the record and will not be filed with
the ODRA, except in connection with a
motion or other permissible filing. Des-
ignated, relevant portions of such doc-
uments may be filed, with the permis-
sion of the ODRA.
(e) The Director of the ODRA shall
assign a DRO or a Special Master to
conduct adjudicatory proceedings, de-
velop the administrative adjudication
record and prepare findings and rec-
ommendations for the review of the
ODRA Director or the Director’s des-
ignee.
(f) The DRO or Special Master may
conduct a status conference(s) as nec-
essary and issue such orders or deci-
sions as are necessary to promote the
efficient resolution of the contract dis-
pute.
(g) At any such status conference, or
as necessary during the Adjudicative
Process, the DRO or Special Master
will:
(1) Determine the appropriate
amount of discovery required;
(2) Review the need for a protective
order, and if one is needed, prepare a
protective order pursuant to § 17.9;
(3) Determine whether any issue can
be stricken; and
(4) Prepare necessary procedural or-
ders for the proceedings.
(h) Unless otherwise provided by the
DRO or Special Master, or by agree-
ment of the parties with the concur-
rence of the DRO or Special Master, re-
sponses to written discovery shall be
due within thirty (30) business days
from the date received.
(i) At a time or at times determined
by the DRO or Special Master, and in
advance of the decision of the case, the
parties shall make individual final sub-
missions to the ODRA and to the DRO
or Special Master, which submissions
shall include the following:
(1) A statement of the issues;
(2) A proposed statement of undis-
puted facts related to each issue to-
gether with citations to the adminis-
trative record or other supporting ma-
terials;
(3) Separate statements of disputed
facts related to each issue, with appro-
priate citations to documents in the
Dispute File, to pages of transcripts of
any hearing or deposition, or to any af-
fidavit or exhibit which a party may
wish to submit with its statement;
(4) Separate legal analyses in support
of the parties’ respective positions on
disputed issues.
(j) Each party shall serve a copy of
its final submission on the other party
by means reasonably calculated so that
the other party receives such submis-
sions on the same day it is received by
the ODRA.
VerDate Mar<15>2010
10:12 Mar 18, 2014
Jkt 232046
PO 00000
Frm 00131
Fmt 8010
Sfmt 8010
Y:\SGML\232046.XXX
232046
pmangrum on DSK3VPTVN1PROD with CFR
| Previous Page | Page 130 | Next Page |