119
Federal Aviation Administration, DOT
§ 17.29
name, address, telephone and Fax num-
bers of the contractor’s legal represent-
ative(s) (if any) for the contract dis-
pute;
(2) The contract number and the
name of the Contracting Officer;
(3) A detailed chronological state-
ment of the facts and of the legal
grounds underlying the contract dis-
pute, broken down by individual claim
item, citing to relevant contract provi-
sions and attaching copies of the con-
tract and other relevant documents;
(4) Information establishing the
ODRA’s jurisdiction and the timeliness
of the contract dispute;
(5) A request for a specific remedy,
and the amount, if known, of any mon-
etary remedy requested, together with
pertinent cost information and docu-
mentation (
e.g., invoices and cancelled
checks). Supporting documentation
should be broken down by individual
claim item and summarized; and
(6) The signature of a duly authorized
representative of the initiating party.
(b) Contract disputes shall be filed at
the following address: ODRA, AGC–70,
Federal Aviation Administration, 800
Independence Avenue, SW., Room 323,
Washington, DC 20591; Telephone: (202)
267–3290, Fax: (202) 267–3720.
(c) A contract dispute against the
FAA shall be filed with the ODRA
within two (2) years of the accrual of
the contract claim involved. A con-
tract dispute by the FAA against a
contractor (excluding contract disputes
alleging warranty issues, fraud or la-
tent defects) likewise shall be filed
within two (2) years of the accrual of
the contract claim. If an underlying
contract entered into prior to the effec-
tive date of this part provides for time
limitations for filing of contract dis-
putes with the ODRA, which differ
from the aforesaid two (2) year period,
the limitation periods in the contract
shall control over the limitation period
of this section. In no event will either
party be permitted to file with the
ODRA a contract dispute seeking an
equitable adjustment or other damages
after the contractor has accepted final
contract payment, with the exception
of FAA contract disputes related to
warranty issues, gross mistakes
amounting to fraud or latent defects.
FAA contract disputes against the con-
tractor based on warranty issues must
be filed within the time specified under
applicable contract warranty provi-
sions. Any FAA contract disputes
against the contractor based on gross
mistakes amounting to fraud or latent
defects shall be filed with the ODRA
within two (2) years of the date on
which the FAA knew or should have
known of the presence of the fraud or
latent defect.
(d) A party shall serve a copy of the
contract dispute upon the other party,
by means reasonably calculated to be
received on the same day as the filing
is received by the ODRA.
(e) With the exception of the time
limitations established herein for the
filing of contract disputes, the ODRA
retains the discretion to modify any
timeframe established herein in con-
nection with contract disputes.
§ 17.29
Informal resolution period.
(a) The ODRA process for contract
disputes includes an informal resolu-
tion period of twenty (20) business days
from the date of filing in order for the
parties to attempt to informally re-
solve the contract dispute either
through direct negotiation or with the
assistance of the ODRA. The CO, with
the advice of FAA legal counsel, has
full discretion to settle contract dis-
putes, except where the matter in-
volves fraud.
(b) During the informal resolution
period, if the parties request it, the
ODRA will appoint a DRO for ADR who
will discuss ADR options with the par-
ties, offer his or her services as a po-
tential neutral, and assist the parties
to enter into an agreement for a formal
ADR process. A person serving as a
neutral in an ADR effort in a matter
shall not serve as an adjudicating DRO
or Special Master for that matter.
(c) The informal resolution period
may be extended at the request of the
parties for good cause.
(d) If the matter has not been re-
solved informally, the parties shall file
joint or separate statements with the
ODRA no later than twenty (20) busi-
ness days after the filing of the con-
tract dispute. The ODRA may extend
this time, pursuant to § 17.27(e). The
statement(s) shall include either:
VerDate Mar<15>2010
10:12 Mar 18, 2014
Jkt 232046
PO 00000
Frm 00129
Fmt 8010
Sfmt 8010
Y:\SGML\232046.XXX
232046
pmangrum on DSK3VPTVN1PROD with CFR
| Previous Page | Page 128 | Next Page |